Decision Maker: Cabinet
Decision status: Information Only
Is Key decision?: No
Is subject to call in?: Yes
Decision made
1. That the contract for the completion of the cycle and pedestrian route from Penwortham Priory Park to Howick as part of the Green links network be awarded to Wade Group for the sum of £314,415 following a tender exercise carried in accordance with the Council’s contract procedure rules.
2. The capital budget for the ‘Green Link - Penwortham Holme to Howick’ scheme is increased to £314,415 to match the tender price, with a transfer of £64,415 from the unallocated green links budget.
Report author: Neil Anderson
Publication date: 25/03/2022
Date of decision: 23/03/2022
Decided at meeting: 23/03/2022 - Cabinet
Effective from: 02/04/2022