Issue details

Worden Hall Procurement Strategy

To approve the proposed procurement strategy for the refurbishment of Worden Hall project.

Procurement Strategy set out below:

Appointment of project management and cost consultancy support through a waiver.

Appointment of a design team (Architect (incl Principal Designer duties, structural engineer and mechanical, electrical and plumbing consultant) via a competitive tendering exercise via the Chest to complete the stage 4 design. These will be invited tenders. The evaluation criteria used for the design team will be 60% Cost, 40% quality

Appointment of services which allow advanced works to be progressed on site.

Appointment of a Contractor using a traditional procurement route to deliver the works via the Rise Construction Framework, using an evaluation criterion of 70% cost, 30% quality.

Decision type: Key

Reason Key: Expenditure/Savings > £100,000;

Decision status: Recommendations Approved

Notice of proposed decision first published: 06/01/2021

Decision due: 6 Jan 2021 by Cabinet Member (Finance, Assets and Public Protection)

Lead member: Cabinet Member (Finance, Assets and Public Protection)