To approve the proposed procurement strategy
for the refurbishment of Worden Hall project.
Procurement Strategy set out below:
Appointment of project management and cost consultancy support
through a waiver.
Appointment of a design team (Architect (incl Principal Designer
duties, structural engineer and mechanical, electrical and plumbing
consultant) via a competitive tendering exercise via the Chest to
complete the stage 4 design. These will be invited tenders. The
evaluation criteria used for the design team will be 60% Cost, 40%
quality
Appointment of services which allow advanced works to be progressed
on site.
Appointment of a Contractor using a traditional procurement route
to deliver the works via the Rise Construction Framework, using an
evaluation criterion of 70% cost, 30% quality.
Decision type: Key
Reason Key: Expenditure/Savings > £100,000;
Decision status: Recommendations Approved
Notice of proposed decision first published: 06/01/2021
Decision due: 6 Jan 2021 by Cabinet Member (Finance, Assets and Public Protection)
Lead member: Cabinet Member (Finance, Assets and Public Protection)
Contact: Ben Storey, Democratic and Member Services Officer Email: ben.storey@southribble.gov.uk.