Decision made
1. To approve a 2-stage tender process.
2. To approve the tendering of the scheme to appoint a contractor at RIBA stage 3.
3. To approve the use of the Northwest Construction Hub Framework, with an evaluation weighting of 70% quality (includes 20% Social Value) and 30% cost as stipulated by the Northwest Construction Hub.
4. To approve the use of the NEC4 Engineering and Construction form of contract to appoint a Contractor.
5. To delegate the award of a contract for stage 1 and stage 2 to the Cabinet Member (Finance, Property and Assets).