Issue - decisions

Worden Hall Procurement Strategy

06/01/2021 - Worden Hall Procurement Strategy

The proposed procurement strategy for the refurbishment of Worden Hall project has been approved.

 

Procurement Strategy set out below:

 

Appointment of project management and cost consultancy support through a waiver.

 

Appointment of a design team (Architect (incl Principal Designer duties, structural engineer and mechanical, electrical and plumbing consultant) via a competitive tendering exercise via the Chest to complete the stage 4 design. These will be invited tenders. The evaluation criteria used for the design team will be 60% Cost, 40% quality

 

Appointment of services which allow advanced works to be progressed on site.

 

Appointment of a Contractor using a traditional procurement route to deliver the works via the Rise Construction Framework, using an evaluation criterion of 70% cost, 30% quality.