Annual and Period 2 (Jan - Mar 2020) Performance Monitoring Report 2019/20

Meeting: 24/06/2020 - Cabinet (Item 106)

106 Annual and Period 2 (Jan - Mar 2020) Performance Monitoring Report 2019/20 pdf icon PDF 595 KB

Report of the Interim Chief Executive attached.

Additional documents:

Decision:

Decision made (Unanimously):

 

1.    That the recommendations made by the Scrutiny Budget and Performance Panel are accepted by Cabinet.

2.    That Cabinet considers and comments on the report.

 

 

Minutes:

The Leader of the Council presented the report of the Interim Chief Executive which provided a summary of performance against the Corporate Plan during quarter 4 ending 31 March 2020 (period 2).

It was reported that overall performance during quarter 4 of 2019/2020 had been good with a number of key successes and objectives completed and the majority of projects and activities on track.  4% of projects were completed, 9% succeeding, 70% on track, 15% off track and 2% yet to start.

Reference was made to the impact of the COVID-19 pandemic and steps now being taken to move to the recovery phase.  Cabinet had commenced work reviewing the Council’s corporate priorities and re-freshing the corporate plan in light of COVID-19.  The acceleration of the Digital to Improve programme to facilitate homeworking for employees was commended.  Cabinet Members praised employees across the Council for maintaining services and also working on the community and business hubs.

The Leader reported on the recommendations of the Scrutiny Budget and Performance Panel which had considered the report the previous Monday.  The Leader confirmed that he accepted all the recommendations made by the Scrutiny Panel.

Decision made (Unanimously):

That the quarter 4 (period 2) performance monitoring report for 2019/2020 be noted.

Reason(s) for the decision:

The Council’s performance framework sets out the process for reporting progress against the objectives of the Corporate Plan.  All reports will continue to be considered by the Council’s Leadership Programme Board, Scrutiny Budget and Performance Panel, Cabinet and a year-end report presented to Full Council.

Alternative options considered and rejected:

Not applicable.

 


Meeting: 22/06/2020 - Scrutiny Budget and Performance Panel (Item 5)

5 Year End and Quarter 4 (Jan - Mar 2020) Performance Monitoring Report 2019/20 pdf icon PDF 595 KB

Report of the Interim Chief Executive attached.

Additional documents:

Minutes:

The Panel considered a report of the Interim Chief Executive which outlined the Council’s performance against the delivery of the Corporate Plan projects and objectives during Quarter 4 (Jan-March 2020).

 

Overall, performance of the projects was good, with 4 of 43 succeeding and 32 on-track.

 

Given recent issues surrounding the council’s Annual Governance Statement, members of the Panel welcomed assurances by the Shared Services Lead for Partnerships and Transformation that the data provided in the performance monitoring report was robust.

 

Discussion largely focused on the impact of the COVID-19 pandemic on the Council’s performance and members were advised that, although a significant financial impact was anticipated in the next year, the pandemic had a minimal impact on performance in Quarter 4. This was largely because the virus had not peaked during the quarter.

 

Members noted that a member working group on business recovery post-COVID-19 had been established to look at how the Council could provide local businesses with support and access to funding. Members were also informed that the Council was still in the ‘containment’ phase and that emphasis was on maintaining service delivery whilst adhering to new health and safety measures as advised by government.

 

It was acknowledged that some of the targets within the Corporate Plan would be reviewed as a result of COVID-19 and as part of a refresh of the Corporate Plan in September 2020, including resource allocation. Further information on this would be provided to the next meeting of the Scrutiny Budget and Performance Panel.

 

In response to queries around the financial impact on COVID-19 on performance, members were informed that there had been some savings as a result of services being online-only and that the council had received £1 million in central government grants to manage the crisis.

 

Members noted that the surplus site review was off-track and enquired as to whether this was due to issues with capacity. Whilst it was acknowledged that the team was not fully staffed, an additional staff member had commenced work on the project. The task was identified as a priority by the Leader of the Council and the Interim Chief Executive.

 

A key line of enquiry focused on the holiday hunger scheme and its 14.7% redemption rate. In response, numerous challenges were acknowledged with regards to the scheme including accessibility, as many families did not shop where the vouchers were redeemable, and demographic diversity across the borough. Members were assured that the council had supplemented the scheme with additional food packages where needed. 

 

In response to queries regarding the MH2K project, which was listed as being off-track, it was recognised that COVID-19 had impacted recruitment to the Youth Engagement Officer post but that this would begin again soon. The project was ongoing and further detail would be provided when appropriate. 

 

The Panel also requested further information on the cost breakdown for the implementation of Tempo time credits.

 

Further to discussion, members sought assurances that the appropriate resources were in place to deliver the council’s Corporate Plan. In  ...  view the full minutes text for item 5