Decision details

South Ribble Extra Care Scheme – West Paddock

Decision Maker: Cabinet, Council

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To present the masterplan options and business case

Decision:

Decision made

 

1.      To approve the progression of design option 3 outlined in this report.

 

2.     To note that £200k of the allocated £10 million budget will be drawn upon to deliver the next stage of the design (RIBA Stage 2 and 3) and contractor procurement process.

 

3.     To note the current estimated project cost to deliver the 72 unit scheme is £14.260 million.

 

4.     To acknowledge that the further design works set out in paragraph 4 are required to verify the projected project cost of £14,260 million, and that further updates on the costs will be brought back when the next stage of design work has been progressed.

 

 

 

 

 

 

Report author: Rachel Salter

Publication date: 16/07/2021

Date of decision: 14/07/2021

Decided at meeting: 14/07/2021 - Cabinet

Effective from: 24/07/2021

  • Restricted enclosure  View reasons restricted
  • Restricted enclosure  View reasons restricted
  • Restricted enclosure  View reasons restricted
  • Restricted enclosure  View reasons restricted
  • Restricted enclosure  View reasons restricted
  •