Decision details

Upgrade of Current HR System to a Hosted Environment

Decision Maker: Interim Chief Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Decision:

Approval granted to:

 

1.    Upgrade the HR System and use £9,500 capital funds from the ICT unallocated fund for the implementation associated with this upgrade and add £5,188 to the ICT Revenue Budget per annum from 2020/21 onwards.

 

2.    Enter into a 27-month contract for the upgraded system at a cost of £61,000.

Publication date: 07/11/2019

Date of decision: 07/11/2019

Effective from: 15/11/2019

Accompanying Documents: