Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
1. To approve Stage 2 design;
2. To approve the progression onto the next stage of the design development (Stage 3);
3. To acknowledge that the cost estimate is currently £15,854,139 which exceeds the approved capital budget of £10 million;
4. To note that the proposed funding intervention from Homes England and the additional Section 106 monies addresses the increased delivery costs to ensure that the additional Council contribution is kept to a minimum;
5. To acknowledge that a further report will be submitted to Council in April 2022 to approve the budget;
6. To acknowledge that the proposed stage works will be undertaken within the current approved budget; and
7. That a savings analysis (i.e. in terms of the effect on costs and resources for the NHS and Health and Social Care system) as a result of the scheme be provided to members.
Report author: Looqman Mulla
Publication date: 21/01/2022
Date of decision: 19/01/2022
Decided at meeting: 19/01/2022 - Cabinet